MARION COUNTY I-24 TDOT Maintenance eastbound from MM 134.3 to MM 142:Â Night work paving various spots on the Interstate. Work will begin 6/9/2024 starting 6pm -6am Work will begin 6/10/2024 6pm -6am Work will begin 6/11/2024 6pm -6am
MARION COUNTY I-24 (US-64) rockfall mitigation westbound between MM 136.2 and MM 140.3: The contractor will be running a mobile operation on 06/09/24, from 7 PM – 6 AM, to install rumble strips on I-24 WB near MM 137 in Marion County. Also, on 06/10/24 and 06/11/24 from 9 AM – 4 PM, on I-24 WB near MM 137 the contractor will be setting up single lane closures leaving two lanes open to traffic to install thermo paint and snowplowables. Please use caution when driving through the work zones.
MARION COUNTY I-24 from east of Big Fiery Gizzard Creek (MM 146) to near SR-27 (US-72, MM 152):Â The contractor will be working on I-24 EB and WB from MM 146 to MM 152.
This work will require single lane closures leaving one lane open to traffic. Then they will begin resurfacing operations on 06/09/24 and work Sunday nights through Friday nights from 7 PM – 6 AM each night until work is completed. No work will occur on Saturday nights. THP and truck mounted attenuators will be on site during the work.
SEQUATCHIE COUNTY SR-111 sinkhole and culvert repair at LM 3.3:Â The contractor will be repairing a sinkhole and culvert on SR-111 near L.M. 3.3 in Sequatchie County. This work has required left lane closures for the Northbound and Southbound traffic, leaving one lane open in each direction. Please use caution when driving through the work zone as there is a lane shift to be aware of.